2. 161 KV Transmission line between Karpower ship to Smelter II Substation in Tema.
A 10 km long transmission line consisting of 22 Lattice Towers and 2 towers mounted at sea. It was constructed in 6 months and was completed and commissioned in 2016. These transmission lines connect the GRIDCo’s substation in Tema to the Karpower ship.